Company overview
One of Europe’s largest public charging networks
Allego is one of Europe’s largest public EV charging networks, operating in 15 European countries and handling around 1.3 million charging sessions a month, from fast-charging hubs along motorways and key locations across Europe to on-street charging in Dutch cities.
Drivers reach it through the Allego app, through payment cards at the charger, and through roaming: a card or app from an e-mobility service provider (eMSP) that they expect to work at every Allego station, every time.
Why AMPECO
The decision to move to a new CPMS
Allego ran a formal RFP, judging platforms on their migration track record, standards compliance and how well they would integrate with its existing operational and enterprise systems and its hardware. Its team also visited AMPECO in Sofia to meet the engineering, product and migration teams who would deliver the project.
Allego and AMPECO announced the partnership in July 2026. By then, the two teams were already at work on the migration.
"From our perspective, AMPECO offered the strongest functional fit for our business. The platform did not just look good on paper, it demonstrated depth across the core CPMS capabilities needed to operate and scale a large charging network, which gave us confidence that it could support both current and future requirements."
The scope
A migration that included more than chargers
A platform move for an operator of this size touches every relationship the network has. For Allego that meant:
01
Charge points
32,000+ EVSEs across 15 countries.
02
Roaming partners
70+ roaming connections, including three roaming hubs that on their own link Allego to more than 400 roaming partners.
03
Payments
Payment terminals of several models, connected to several payment providers, and Allego’s ad hoc payment portal.
04
Billing and business systems
Allego’s billing process and the systems it feeds.
05
Site hosts
The businesses that host Allego chargers at their locations.
All of it had to move in the same cutover.
Preparing for the switch
Five months of joint preparation
The cutover went smoothly because the two teams spent the five months before it making sure the night would hold no surprises. Allego and AMPECO teams worked to one principle: every difficult question gets asked, and answered, before migration day.
01
End of May
Scoping workshops in Arnhem, The Netherlands
Both teams agreed what had to move and what had to work on day one. Allego’s network would move as it runs today, and new capabilities would come after go-live.
02
June – September
Joint workstreams with owners on both sides
Roaming, data migration, payments, billing, business system integrations, and end-to-end hardware and firmware testing, with sign-off on every charger model. Allego’s teams mapped their data, translated tariffs and partner contracts into AMPECO’s model, and trained the people running the network on the new platform.
03
Final three weeks
Every flow tested end to end
Every flow was tested end to end before anything moved in production. That included chargers, cards, app, Plug & Charge, payments and roaming.
04
Cutover night
Planned line by line
A checkpoint and a named owner for every activity, and a go or no-go decision from Allego’s leaders at each step. Roaming partners knew in advance what to expect, and drivers were warned through the Allego app.
What held the plan together was the way the two teams worked as one. Allego’s technical and business people stayed close to the work and shared what they knew, so any problem that may arise belonged to the joint team. The tight scope and the fixed date kept everyone’s attention on what had to work on day one. Decisions were made the day they were needed, and blockers were cleared within hours instead of waiting for the next steering meeting. Allego’s leaders backed this by giving the people closest to the operation the authority to act.
Roaming
Taking roaming off switch day
A migration this size usually means reconnecting dozens of roaming partners from scratch: new handshakes, tests and weeks of work. The standard advice is also to take a new CPO ID, the code that identifies an operator to its roaming partners. Allego wanted to keep its own. Its ID, ALL, is one partners have known for years, and it runs through every Allego charger ID, where it spells out the brand name.
"Traditionally, someone from roaming would need to schedule more than 50 different handshakes with 50 different partners all over Europe, on switch day."
Working closely with Allego’s technical team, AMPECO built a new way to migrate roaming that kept Allego’s CPO ID, saved its partners from reconnecting, and caused zero roaming disturbance for partners and drivers. The most important partners ran a joint test with AMPECO’s roaming team; the others kept their existing connection details.
AMPECO can now apply the same approach to future migrations, planned around each operator’s roaming setup and delivered together with its technical team, as it was with Allego.
The night of the switch
One open call, eight batches
27 – 28 OCTOBER 2026
Allego opened its Arnhem head office specially for the night, and about 40 Allego people worked through it, alongside part of the AMPECO team. From about one in the morning until nine, one open call linked the office with everyone working remotely and with testers in six of Allego’s key markets, who waited at chargers to start sessions as soon as their stations came back.
Allego chose the early hours, when most cars on its AC chargers are plugged in overnight and their drivers are asleep. At the planned moment in the cutover plan, the Allego app sent its users a push message announcing maintenance on the network between 2 and 4 in the morning.
The chargers moved in eight batches of about 2,000. Sessions were stopped on the previous platform, chargers were rebooted, and Allego’s team pointed the first batch at AMPECO. That batch was chosen to be as varied as possible, covering different countries, charger types and kinds of site.
On the big screens in the office, showing live sessions, authorisations and the main dashboard, the first chargers appeared on the AMPECO platform, and the room gathered round to watch. In the Allego car park, where some of the first-batch chargers stand, the teams tested with real cars.
Every flow was then tested end to end, in every country: RFID cards, the Allego app, roaming cards, Plug & Charge, payment terminals and ad hoc payments. Only once each one was signed off did Allego’s leaders give the go for the rest. The remaining seven batches followed at a deliberate pace, because each batch means thousands of reboots and a wave of updates to roaming partners, and the teams did not want to flood anyone’s systems.
While the batches moved, drivers kept charging: RFID cards, which start most sessions at Allego, worked all night.
The results
By the morning of 28 October
| 32,000+ | EVSEs in 15 countries running on AMPECO | After a cutover that took less than two hours. |
| 70+ | Roaming connections came across | Including three roaming hubs, with zero roaming disturbance for roaming partners and drivers. Allego kept its CPO ID. |
| Same night | Plug & Charge, payment terminals and ad hoc payments | All moved in the same cutover, with existing Plug & Charge certificates carried across. |
| Fewer calls | Than on a normal day | Allego’s call centre took fewer driver calls during the cutover than on a normal day. |
More than 100 people across Allego’s Operations, IT, Charging Technology, Procurement, Finance, Energy Platform and Marketing teams took part, alongside AMPECO and Allego’s technology partners.
"This was far more than a software migration. We changed one of the technological foundations of our charging network. The result reflects months of preparation, rigorous testing and, above all, exceptional teamwork across departments, countries and companies. Ultimately, this migration strengthens our ability to scale, improve operational excellence, and deliver an even better charging experience for our customers."
What comes next
What comes next for Allego
With the migration done, Allego can turn its effort to what it set out in July: an outstanding charging experience for every driver on its network, distinctive propositions for its business partners, and energy intelligence and smart charging, which it expects to shape the next phase of the market.
"Partnering with AMPECO gives us a modern, future-proof platform that allows us to focus on what matters most: delivering an exceptional charging experience for every driver who uses our network."
With AMPECO maintaining the platform layer, from standards and compliance to hardware integration, Allego’s technology teams can work on the integrations, data and driver experiences that differentiate its network, and respond faster when regulation changes. New capabilities can be switched on from AMPECO’s Marketplace instead of being built from scratch. Allego’s operations teams already work with CoOperator, the AI operations agent built into the platform, which runs diagnostics across the network and helps catch faults before they reach support teams.
Lessons
What other operators can copy
Allego ran the migration as a company-wide effort. Every department had a part in it, and leadership trusted the operational teams to make decisions and cleared blockers quickly when they came up, without adding layers of approval.
01
Freeze the scope. Decide early what has to work on day one, go live with it, and improve from there.
02
Use the migration to retire processes that were not working, before they reach the new platform.
03
An owner on both sides of every workstream, so each problem belongs to the joint team.
04
A varied first batch, across countries, charger types and kinds of site, with every flow tested on it before a go or no-go on the rest.
05
Paced batches. Each one means thousands of reboots and a wave of roaming updates, so partners’ systems need room to absorb them.
06
A cutover plan written line by line, with a checkpoint and a named owner for each step.
For AMPECO, Allego’s migration answers the question that holds many large operators back: whether a network this size, with everything connected to it, can change platforms without its drivers, partners and site hosts paying for the move. Allego’s network gives the answer every day: a pan-European network migrated in less than two hours and running on AMPECO since the morning of 28 October.